Oracle Is Trucking In Natural Gas to Keep Its AI Data Centers on Schedule
Alpha Vantage · 24/7 Wall St. · · AI-summarised by FinFlash
Oracle is using trucked-in natural gas to power its AI data centers due to delays in pipeline construction and permits, despite the significantly higher cost, to meet contractual delivery dates. This workaround is being implemented at three sites, including Project Jupiter in New Mexico, highlighting the company's commitment to its $664 billion backlog of AI capacity.