Friday pre-hearing to address DTE plan including Handy Township power plant

Alpha Vantage · thelivingstonpost.com · · AI-summarised by FinFlash

State regulators are holding a remote pre-hearing on Friday, Oct. 23, 2026, to discuss DTE Electric's application for a proposed $3.9 billion natural-gas power plant in Handy Township. The 1,400-megawatt facility would be a major electricity-generating operation for Livingston County, aiming to begin commercial operations by late 2031, subject to approvals.